powerpath DC
Image credit: Stock

The Public Service Commission of the District of Columbia in the US has approved the next set of grid modernisation recommendations for the District of Columbia, in its grid modernisation proceeding, Power Path DC.

The Order addresses the remaining recommendations from the PowerPath DC stakeholder process, including:

  • Enhancing data access for all residential customers through Pepco’s “Green Button Connect My Data”;
  • Issuing a notice of inquiry, inviting stakeholder input on distributed energy resources (DERs) ownership rules;
  • Directing Pepco and Washington Gas to make system-level data available on their websites; and
  • Aligning Power Path DC vision statement with the District’s clean energy and climate commitments.

Related Stories:
Second-largest US utility commits to 2050 net zero target
US utilities ready for a pandemic-stricken summer says NERC
102MW Of community solar projects announced for upstate New York

In January, the Commission took the first in a series of steps to advance grid modernisation in the District. The January Order approved several stakeholder recommendations:

  • Adopting a new distribution system planning process to allow open and transparent stakeholder engagement;
  • Launching the Power Path DC pilot projects governance board;
  • Developing a new retail choice website, DC Power Connect, that will serve as a central clearinghouse for third-party energy suppliers; and
  • Establishing a separate microgrid proceeding.

Chairman Willie L. Phillips stated, “By aligning Power Path DC with the District’s clean energy goals, we take another important step towards achieving our strategic vision of a customer-focused, clean and renewable energy grid for the District.”

Originally published on POWERGRID International.