East Anglia One
East Anglia One wind farm. Image credit: Wikimedia

ScottishPower Renewables and Macquarie’s Green Investment Group (GIG) have successfully installed every single turbine on the East Anglia ONE offshore windfarm – another major milestone for the project as it approaches completion.

Beginning in June 2019, a total of 102 Siemens Gamesa SWT-7.0-154 offshore wind turbines have been installed at the windfarm site, 43km off the Suffolk coast. Installation was undertaken by Siemens Gamesa using the Sea Installer and Sea Challenger vessels, operated by DEME.

Related Stories:
Solar and wind are the cheapest new sources of energy says BNEF
Global offshore wind needs 77,000 trained on-site workers by 2024 – report
COVID-19: Surge in negative wind energy pricing

All turbine components were pre-assembled and loaded out from Peel Ports Great Yarmouth, following ScottishPower Renewables’ £5 million co-investment in the port to prepare it for construction and marshalling activity. The components consist of 75-metre fibre glass blades, tower sections and nacelles (the head of the turbine), which have been on view along the Great Yarmouth seafront and skyline as the 90-metre-high towers were constructed on the quayside.

Each of the 306 turbine blades were manufactured by Siemens Gamesa at its specially-built factory in Hull, England; while some of the towers were produced in Machrihanish, Scotland by CSWind UK. The work that took place at Peel Ports was supported by several local companies and personnel employed by Siemens Gamesa, including Lowestoft-based Delpro Wind and CLS Global Solutions, based in Great Yarmouth.

Once fully operational, the facility will produce 714MW of clean energy annually – enough to power the equivalent of more than 630,000 homes.

As well as the successful turbine installation, ScottishPower Renewables reached a company milestone during construction, installing its 1,000th MW of offshore wind power on the East Anglia ONE site. Furthermore, Siemens Gamesa notched up the installation of their 1,000th Direct Drive offshore turbine during this project.

Charlie Jordan, East Anglia ONE Project Director at ScottishPower Renewables, said: “Successful installation of all the turbines is a tremendous achievement for the East Anglia ONE project. It brings us another step closer to completion when the windfarm will be producing the clean, renewable energy the UK needs to decarbonise and meet its pledge to reach net-zero by 2050. This project is testament to the leading role East Anglia is playing in offshore wind and is delivering tangible benefits for its people, businesses and communities – including the creation of more than 800 jobs and spending over £70 million with companies across the region.”

Andrew Elmes, East Anglia ONE Senior Project Manager at Siemens Gamesa, added: “Ensuring the safety of our employees, customers and suppliers is at the forefront of all we do. We are proud to be working alongside the entire team to safely manufacture, install, and commission the turbines for East Anglia ONE. It’s been a long, challenging journey so far, with new technology, significant weather conditions, and now COVID-19 to overcome. All these factors make this milestone even more fantastic.

“Through collaboration and drawing on our expertise in offshore wind power, as well as harnessing the vast experience of the UK supply chain, we have been able to safely complete installation in good order and ensure East Anglia ONE will deliver reliable clean energy for generations to come.”